How many days do you have to file a lien without notice of completion filed?

Prepare for the Nevada Contractors License Law Test. Use flashcards and multiple-choice questions with detailed explanations and hints. Ace your exam with confidence!

In Nevada, the law provides specific time frames regarding the filing of a mechanic's lien. When no notice of completion has been filed, a contractor, subcontractor, or supplier has 90 days from the last date of work or materials provided to file a lien against the property. This timeline is crucial for ensuring that parties involved in construction or improvement projects have a legal means to secure payment for their services or materials.

If a notice of completion is filed, the time frame becomes shorter, but the absence of such a notice allows for the full 90 days under which one can assert their right to a lien. Understanding these time limits is essential for contractors and suppliers to protect their interests in the event of non-payment.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy