How long do you have to file a lien claim if no notice of completion is filed?

Prepare for the Nevada Contractors License Law Test. Use flashcards and multiple-choice questions with detailed explanations and hints. Ace your exam with confidence!

In Nevada, the timeframe to file a lien claim when no notice of completion has been filed is indeed 90 days. This 90-day period begins to run from the date the claimant last provided labor or materials to the project. The intent behind this regulation is to ensure that those who contribute labor or materials to a construction project have a reasonable period to seek compensation if they are not paid, especially in cases where a notice of completion has not been filed.

Filing within this timeframe is crucial because if a lien is not filed within the 90 days, the right to place a lien on the property may be lost. This statutory guideline helps to maintain clarity and order in the construction industry, protecting the interests of contractors, subcontractors, and suppliers by enforcing timely claims for payment.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy